After all the floor joists were finished we installed the sewer lines and started sheeting the floor and getting the garage ready to pour the concrete.
Saturday, August 24, 2013
Conejo Foundation
After two weeks of tying rebar together to connect the caissions we poured another 5 concrete truck loads of concrete.
Conejo Foundation
After the concrete pump has placed all of the concrete from 3 concrete trucks only 2 feet of rebar is left sticking up in the air.
Conejo Foundation
Since this lot has very unstable soils we ended up drilling a 35 foot deep hole by 18" wide, then dropped the rebar cage into the hole. We did this 9 times and there were 13 caissons existing.